The 2010 Hardware Commissioning Campaign
started on January 4
The LHC is being prepared for operations at 3.5 TeV:
Sector 81: PIC2 tests successfully performed on RQD/F and RB (at 100A). RQD/F have been brought to injection (PLI1.b3) and then proper heaters firing has been verified. RRR measurement tests are ongoing. Sector 12: Powering in phase II ongoing. nQPS system hooked to the interlock loop. |
Sector 23:
Powering in phase II ongoing. All 13kA circuits have been brought to 2kA. The nQPS system will be interlocked next week.
Sector 34:
Powering Phase II ongoing.
Sector 45:
Powering Phase I almost completed for the three 13kA circuits.
Sector 56:
Quench heaters power supply to be switched on next week.
Sector 67:
Quench heaters power supply to be switched on next week.
last update: 30 Jan 2010, Matteo Solfaroli